Hydro project on Yamuna 'bitter lesson' for those calling it cheap green energy source

By Bhim Singh Rawat* 

The 120 Mw Vyasi HEP built by Uttarakhand Jal Vidyut Nigam Ltd (UJVN Ltd.) in Vikas Nagar tehsil of Dehradun is on its way to become the textbook example of how thoughtlessly pushed hydro power projects are proving a nightmare for local people, a costly affair for the state and the nation and a disaster for free-flowing living river.
The project offers some bitter lessons for the policy-makers, experts and society who have been assuming that hydro power is a cheap, green source of energy and the Run of River (RoR) projects don’t dam and cause much harm to the environment, people or rivers.

Past violations unpunished

Like the case with most of hydro projects in the Himalayan region; the Vyasi HEP too has missed several deadlines and suffered cost escalation from Rs. 936.23 crores in February 2010 to Rs. 1777.30 crores upto September 2021.
While in the making for over a decade, the contractor companies brazenly violated several environmental norms including those meant for safe disposal of tunnel debris and construction muck. The project also caused large scale illegal mining in the Yamuna to secure construction materials from the same Yamuna river.
However, in absence of credible monitoring or compliance mechanism, UJVNL have never been held accountable for the irregularities and destruction. There is no information regarding compensatory afforestation against diversion of about 100 hectares of forest land for the project.

Impact on river, people during filling up

The project was prematurely inaugurated in December 2021 but actually came into operation in April 2022 without addressing the Rehabilitation & Resettlement (R&R) rights of agitating Lohari villagers. About 72 homes of the tribal village and several acres of fertile lands have been drowned into the Vyasi dam. Continuing their struggle, many of the displaced families have still been taking temporary shelter in a nearby school.
Meanwhile, with the project commissioned, the unrealistic claims made by UJVNL have also been exposed while the adverse impacts on river ecology are still unfolding. It all began with mass annihilation of fresh water species including the endangered Mahseer fish in huge numbers both in the impounded as well as flowless Yamuna river downstream the dam.T
he farmers from scores of villages dependent on Katapathar canal suffered lack of irrigation water for about three months as the filling up the giant reservoir decreased water flow into the canal from about average 6 cumecs to 1.5 cumecs only. The situation turned so bad that there were fierce protests forcing UJVNL to attend to farmers’ demand.

Yamuna: Once free flowing, now dammed river

Today, the 86-meter-high gravity dam with a 13.69 million cubic metre gross storage capacity has confined a free flowing and living Yamuna into a about 4 km long reservoir extending along 73 hectares of river banks. With this precious fresh water eco-system including riverine vegetation has been lost into the stagnant water body. Notably, this stretch of Yamuna has been among few unthreatened habitats of Mahseer fish.
There has been no independent assessment on ecological impact of the project before the construction and no plan to address the same even after its being operational. UJVNL has built a fish tank downstream the dam with a plan to rear the fish there and release them in the river. The tank is serving no purpose currently.

Dam filled but the project lacks water to run

Ever since its commissioning, the project has been struggling to generate the power according to its designed capacity of 120 MW as there is lack of required flow in the river. Except for few weeks in monsoon months, the UJVNL has been able to run the project only to a quarter or at most half its installed capacity.
Even during monsoon season, power generation has been compromised by the amount of silt and flood level in the river. The water flow in the river during winter are usually lower than monsoon and summer.
In the peak summer season of June 2023, the Vyasi HEP is kept operational for just about 10 hours from 01:00 pm to 11:00 pm generating about 45 Mw for about 7 initial hours and 120 MW for about last 3 hours. The generated power is being sold to the Power Transmission Corporation of Uttarakhand Ltd. (PTCUL) at Rs 7 per unit. The PTCUL further transmits and distributes the power to the Uttarakhand Power Corporation Limited (UPCL) or national grid according to the demand placed which varies on daily basis.
Clearly, the Vyasi HEP is somehow managing to operate at less than half of its installed capacity even in summer. The main reason behind the gross under performance is outdated, biased assessment reports based on which the project was pushed, these reports grossly underestimated significant decline in overall flows in Yamuna and its tributaries over the years on account of man-made reasons as well as climate change.
Muck from Vyasi HEP tunnel dumped close to the river bank
Given the ongoing and planned tapping of feeding streams and Yamuna itself for growing potable water and irrigation requirements in the catchment, there is likely to be a further decline in flowing water in the river in future. A case in point is Rs. 144 crore Mussoorie water project which is in final stages and would pump out 12 MLD of Yamuna water some 20 km uphill upstream from the Vyasi HEP site.

A farce called e-flows

In the name of environmental flows (e-flows), the UJVNL has been releasing just 5 cumecs of water downstream the river through an inbuilt pipe in dam structure. More than half this e-flow is comprised of the seepages collected inside the dam. The dam gates are opened only for repairing, desiltation purposes or when dam is filled to its capacity.
Project was prematurely inaugurated in Dec 2021 and came into operation in April 2022 without addressing the R&R rights
As a result, about 6 km long stretch of the river between dam at Juddo and power station at Hathyari is deprived of essential flows where the aquatic lives struggle to survive in the almost flowless river. This is despite two perennial streams joining the Yamuna between the dam and power station of the project.
As per local people, the situation was even worse in 2022-23 winter months than the current summer season. They said that the mighty Yamuna was reduced to a trickle between project dam and Dakpathar barrage causing frequent deaths of fish and other aquatic lives. The UJVNL and Central Water Commission (CWC) are required to remedy the situation on urgent basis.

Hungry waters turning river into danger zone

Another serious problem created by the Vyasi HEP is that the project has converted the otherwise safe river banks into a danger zone for local people, tourists and domestic animals. The silt free water known as hungry waters discharged from the power station of the project has been causing sudden fluctuations in the river which is detrimental to the proliferation of the aquatic eco-system.
The project has altered the natural flowing pattern of the Yamuna and greatly increased the eroding capacity of the river which is evident from the fact that the river is dangerously eating into its left bank along the Bausan village, downstream the project.
The average inflows in the river during third week of Jun 2023 have been around 30 cumecs. While the dam has strangulated the river of flows, the power station, when it operates, has been dumping about twice or three time more silt free water than the river would have carried in natural state.
The UJVNL has placed several warning boards, installed sirens at three places and deployed a mobile van plying along the 20 km of the project affected area alerting people to stay away from the river. But these measures appear inadequate to prevent any untoward incident.
The local people have found the deafening noise of the sirens annoying, sometimes blaring out in the dead of night which has been toned down following complaints. The farmers and fishermen have been trying to get accustomed with artificially controlled flows and floods in the river. They have to stay watchful for their wards and cattle whenever the sirens blare out

Vyasi HEP disaster preparedness lagging behind

This is so far the tallest and biggest dam on main stem of Yamuna in a geologically and climatically vulnerable region. The project area has been riddled with new and old recurring landslides. Only in August 2021, there have been cloud bursts induced flash floods both at the power station and dam area impacting the project. Despite this. UJVNL has not installed the Early Warning System (EWS).
Hiding Behind Lakhwar Dam
As the adverse impacts and failures of Vyasi HEP have come in open, the UJVNL and contractors’ lobby have started promoting Lakhwar dam as a panacea for all the shortcomings of the Vyasi HEP. Recently the L&T company is learnt to have secured Rs. 3200 crore tenders for civil construction work of the Lakhwar dam project and has started building shelters for workforce there. The work on the dam is reportedly to begin after the south west monsoon 2023.
The proposed massive 204-m high Lakhwar dam, if built, will further turn more than 40 km stretch of free-flowing Yamuna into a watery grave apart from submerging over 50 villages. Sadly, in the global era of large dam removal and in the face of growing dam induced disasters in Himalayan region, the Indian government is still investing in such multi-billion giant dam project on the basis of four-decade old questionable feasibility and EIA reports to cover up the follies of Vysai HEP instead of learning lessons from it.
---
*Source: South Asia Network on Dams, Rivers and People

Comments

TRENDING

Beyond his riding skill, Karl Umrigar was admired for his radiance, sportsmanship, and affability

By Harsh Thakor*  Karl Umrigar's name remains etched in the annals of Indian horse racing, a testament to a talent tragically cut short. An accident on the racetrack at the tender age of nineteen robbed India of a rider on the cusp of greatness. Had he survived, there's little doubt he would have ascended to international stature, possibly becoming the greatest Indian jockey ever. Even 46 years after his death, his name shines brightly, reminiscent of an inextinguishable star. His cousin, Pesi Shroff, himself blossomed into one of the most celebrated jockeys in Indian horse racing.

Aurangzeb’s last will recorded by his Maulvi: Allah shouldn't make anyone emperor

By Mohan Guruswamy  Aurangzeb’s grave is a simple slab open to the sky lying along the roadside at Khuldabad near Aurangabad. I once stopped by to marvel at the tomb of an Emperor of India whose empire was as large as Ashoka the Great's. It was only post 1857 when Victoria's domain exceeded this. The epitaph reads: "Az tila o nuqreh gar saazand gumbad aghniyaa! Bar mazaar e ghareebaan gumbad e gardun bas ast." (The rich may well construct domes of gold and silver on their graves. For the poor folks like me, the sky is enough to shelter my grave) The modest tomb of Aurangzeb is perhaps the least recognised legacies of the Mughal Emperor who ruled the land for fifty eventful years. He was not a builder having expended his long tenure in war and conquest. Towards the end of his reign and life, he realised the futility of it all. He wrote: "Allah should not make anyone an emperor. The most unfortunate person is he who becomes one." Aurangzeb’s last will was re...

राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी: जल जीवन मिशन के लक्ष्य को पाने समन्वित प्रयास जरूरी

- राज कुमार सिन्हा*  जल संसाधन से जुड़ी स्थायी समिति ने वर्तमान लोकसभा सत्र में पेश रिपोर्ट में बताया है कि "नल से जल" मिशन में राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी साबित हुए हैं। जबकि देश के 11 राज्यों में शत-प्रतिशत ग्रामीणों को नल से जल आपूर्ति शुरू कर दी गई है। रिपोर्ट में समिति ने केंद्र सरकार को सिफारिश की है कि मिशन पुरा करने में राज्य सरकारों की समस्याओं पर गौर किया जाए। 

PUCL files complaint with SC against Gujarat police, municipal authorities for 'unlawful' demolitions, custodial 'violence'

By A Representative   The People's Union for Civil Liberties (PUCL) has lodged a formal complaint with the Chief Justice of India, urging the Supreme Court to initiate suo-moto contempt proceedings against the police and municipal authorities in Ahmedabad, Gujarat. The complaint alleges that these officials have engaged in unlawful demolitions and custodial violence, in direct violation of a Supreme Court order issued in November 2024.

How the slogan Jai Bhim gained momentum as movement of popularity and revolution

By Dr Kapilendra Das*  India is an incomprehensible plural country loaded with diversities of religions, castes, cultures, languages, dialects, tribes, societies, costumes, etc. The Indians have good manners/etiquette (decent social conduct, gesture, courtesy, politeness) that build healthy relationships and take them ahead to life. In many parts of India, in many situations, and on formal occasions, it is common for people of India to express and exchange respect, greetings, and salutation for which we people usually use words and phrases like- Namaskar, Namaste, Pranam, Ram Ram, Jai Ram ji, Jai Sriram, Good morning, shubha sakal, Radhe Radhe, Jai Bajarangabali, Jai Gopal, Jai Jai, Supravat, Good night, Shuvaratri, Jai Bhole, Salaam walekam, Walekam salaam, Radhaswami, Namo Buddhaya, Jai Bhim, Hello, and so on. A soft attitude always creates strong relationships. A relationship should not depend only on spoken words. They should rely on understanding the unspoken feeling too. So w...

Incarcerated for 2,424 days, Sudhir Dhawale combines Ambedkarism with Marxism

By Harsh Thakor   One of those who faced incarceration both under Congress and BJP rule, Sudhir Dhawale was arrested on June 6, 2018, one of the first six among the 16 people held in what became known as the Elgar Parishad case. After spending 2,424 days in incarceration, he became the ninth to be released from jail—alongside Rona Wilson, who walked free with him on January 24. The Bombay High Court granted them bail, citing the prolonged imprisonment without trial as a key factor. I will always remember the moments we spent together in Mumbai between 1998 and 2006, during public meetings and protests across a wide range of issues. Sudhir was unwavering in his commitment to Maoism, upholding the torch of B.R. Ambedkar, and resisting Brahmanical fascism. He sought to bridge the philosophies of Marxism and Ambedkarism. With boundless energy, he waved the banner of liberation, becoming the backbone of the revolutionary democratic centre in Mumbai and Maharashtra. He dedicated himself ...

State Human Rights Commission directs authorities to uphold environmental rights in Vadodara's Vishwamitri River Project

By A Representative  The Gujarat State Human Rights Commission (GSHRC) has ordered state and Vadodara municipal authorities to strictly comply with environmental and human rights safeguards during the Vishwamitri River Rejuvenation Project, stressing that the river’s degradation disproportionately affects marginalized communities and violates citizens’ rights to a healthy environment.  The Commission mandated an immediate halt to ecologically destructive practices, rehabilitation of affected communities, transparent adherence to National Green Tribunal (NGT) orders, and public consultations with experts and residents.   The order follows the Concerned Citizens of Vadodara coalition—environmentalists, ecologists, and urban planners—submitting a detailed letter to authorities, amplifying calls for accountability. The group warned that current plans to “re-section” and “desilt” the river contradict the NGT’s 2021 Vishwamitri River Action Plan, which prioritizes floodpla...

CPM’s evaluation of BJP reflects its political character and its reluctance to take on battle against neo-fascism

By Harsh Thakor*  A controversial debate has emerged in the revolutionary camp regarding the Communist Party of India (Marxist)'s categorization of the Bharatiya Janata Party. Many Communists criticize the CPM’s reluctance to label the BJP as a fascist party and India as a fascist state. Various factors must be considered to arrive at an accurate assessment. Understanding the original meaning and historical development of fascism is essential, as well as analyzing how it manifests in the present global and national context.

Implications of deaths of Maoist leaders G. Renuka and Ankeshwarapu Sarayya in Chhattisgarh

By Harsh Thakor*  In the wake of recent security operations in southern Chhattisgarh, two senior Maoist leaders, G. Renuka and Ankeshwarapu Sarayya, were killed. These operations, which took place amidst a historically significant Maoist presence, resulted in the deaths of 31 individuals on March 20th and 16 more three days prior.

Haven't done a good deed, inner soul is cursing me as sinner: Aurangzeb's last 'will'

Counterview Desk The Tomb of Aurangzeb, the last of the strong Mughal emperors, located in Khuldabad, Aurangabad district, Maharashtra, has this epitaph inscribed on it: "Az tila o nuqreh gar saazand gumbad aghniyaa! Bar mazaar e maa ghareebaan gumbad e gardun bas ast" (the rich may well construct domes of gold and silver on their graves. For the poor folks like me, the sky is enough to shelter my grave).