Tata power has announced to the Union Ministry of Power that Tata Power may be forced to stop operating  its imported coal-based Mundra Ultra-Mega Power Project (UMPP) after February, 2020. It is not only unfortunate but also criminal that irreversible damage has been caused to the fragile ecosystem of Mundra coast for a project that will have a running life of only seven years.
The project has destroyed the environment the economic displacement of the communities affected. Farmers, fish workers, salt pan workers, cattle grazers have suffered irreversible damage to their lives and livelihoods. The outdated open cycle technology used in the plant has destroyed the marine ecology.
Today, thousands of fish workers are struggling to make ends meet due to decline in the fish catch in the area, agricultural land has become saline to ingress of sea water from the intake channel and the grazing land has been acquired for the project. After all this damage, the project didn’t even make any financial sense also.
This project has displaced people, snatched their livelihoods and failed to carry out any genuine consultations. Making matters worse, the plant from the very beginning has been operating at a financial loss following rises in the prices of imported coal. Now, the company may be looking at selling the plant to the government.
This situation points out to many failures on part of the government, financing agencies and company who have clearly failed to conduct due diligence, assess the financial viability of the project and the damage that the project would cause to the people and environment.
The Union Power Ministry’s orders to consumer states Haryana, Rajasthan, Punjab and Maharashtra, which buy power from the Mundra plant, to decide on the matter, or deal with power shortage without Centre’s support are pressure tactics to force consumers states to bear with the losses of the company.
These costs would eventually come to the consumer. In case, the five consumer states allow pass-through of additional fuel cost to consumers, this would mean allowing relief beyond the PPA terms and conditions which would imply passing on to the consumers, commercial risks that were voluntarily assumed by the project developer to win the contract.
The reports that the government may take over the project is of serious concern. The project is a stressed asset. By the end of FY2018-19, the Mundra UMPP, also known as Coastal Gujarat Power, had incurred total retained losses in excess of US$-1.5bn. This is when to combat continual, significant losses the plant, the company imported a higher proportion of lower energy coal in an attempt to reduce fuel costs. The proportion of lower energy coal used at Mundra increased from 20% in 2018 to 42% in 2019.
Governments’ record of running companies profitably has taken a beating in the last many years. Deliberately they have been made to underperform, to pave way for privatization. Examples of BSNL, Air India, MTNL, SAIL and many such flagship companies are well known to all.
The story of Gujarat is not any different. In Gujarat, state run entities (PSUs) incurred losses of Rs 3,813.93 crore in 2017-18 according to a CAG report. The major loss-making state PSUs were GSPC (Rs 1,564 64 crore), Sardar Sarovar Narmada Nigam Ltd (Rs 1,075.8 crore), Bhavnagar Energy Company Ltd (Rs 617.31 crore) Gujarat State Road Transport Corporation (Rs 264.81 crore) and Gujarat Water Infrastructure Ltd (Rs 137.53 crore.
At a time when the government is unable to run the PSUs properly, it doesn’t make any sense to acquire a loss making private company with taxpayers’ money, especially when the prospects of turning it into a profit making one is nearly impossible.
In the worst case scenario, even if the government decides to take up and run the project, it is essential that the technology is changed from open cycle to a closed cycle cooling system for the outlet channel. This step is critical to save the marine life, which in the years of operation of the plant has been destroyed due to discharge hot water into the sea. Over the years, there has been a significant decline in the fish catch and has destroyed the livelihood of thousands of fish workers.
The initiative launched by government of India for facilitating the development of coal-based Ultra Mega Power Plants (UMPPs), each of minimum 4000 MW capacity has been a complete failure. The first UMPP of India, Mundra UMPP was awarded to Tata Power through a competitive tariff-based bidding process.
Mundra UMPP takeover? Govt record of running companies profitably has taken a beating in the last many years
Of the 16 proposed UMPP projects 8 have been cancelled, 4 have been shelved, one is at a pre-permit development sage. Only two projects have been operational, one being Tata Mundra UMPP and other Sasan UMPP. Both projects are under financial distress and have been marred with serious environment and social concerns.
With the scale and design of the Ultra Mega Power Projects they are designed for failures. It is important that the energy security are met in a sustainable manner. It also raises questions about the aggressive development paradigm and inequality in energy access and consumption.
This project also highlights the failure of Multilateral Development Banks, which claim commitment to reducing poverty and promoting sustainable development. Both International Finance Corporation (IFC) and Asian Development Bank (ADB), who have financed this project failed to conduct due diligence.
The financial viability of a project needs to be factored in before a project is sanctioned. This should have included not only the building and operational costs of the project, but also displacement and loss of livelihood and environmental damage. Government subsidies also needed to be factored in.
Negative environmental and social impacts of this project were recognized by audit reports of the Compliance Advisor Ombudsman (CAO) – the independent recourse mechanism for the World Bank’s IFC – and the ADB’s Compliance Review Panel (CRP), following complaints from the communities.
Despite scathing reports from their accountability mechanisms recognizing the non-compliance of environmental and social policies of these institutions, the response of the management was of denial and there was little or no relief for the affected community. The affected community rejected remedial Action Plans that were prepared as a part of the compliance processes as they were mere bandage work.
This is also a reminder of the little or no power these accountability mechanisms of MDBs have, reducing them to merely toothless observers. It is a shame that after nine years of the complaint being filed by the affected community to CAO, and the IFC loan being paid off; in the last monitoring report of the remedial action plan of IFC for the Project remains incomplete.
The complete apathy of the funding institutions led to the fish workers adversely affected by the project file suit against the IFC in federal court in Washington, DC in April 2015. After a long battle a historic decision in February 2019 the US Supreme Court decided that international organizations like the World Bank Group can be sued in US courts, they “don’t enjoy absolute immunity”.
The case will again go back to the lower court for the arguments to establish that in this particular case IFC can be held responsible in the US Courts for the destruction of livelihood of the fishing community of Mundra by lending finance to Tata Mundra Power Project as, now they are stripped of their absolute immunity.
The Tata Mundra UMPP is a complete failure. From the violation of national laws to the failure of to apply the environmental and social safeguards, from environmental and social destruction to financial disaster, to failed policies of energy security, this project is a case study of what should not be done.
But, it is the people of Mundra who have suffered the worst for the wrong decisions of the Government. Whether the government decides to buy the plant or company abandons the project the people continue to suffer and this needs to be addressed immediately.
---
*Machimar Adhikar Sangharsh Sangathan, Kutch, Gujarat

Comments

TRENDING

How the slogan Jai Bhim gained momentum as movement of popularity and revolution

By Dr Kapilendra Das*  India is an incomprehensible plural country loaded with diversities of religions, castes, cultures, languages, dialects, tribes, societies, costumes, etc. The Indians have good manners/etiquette (decent social conduct, gesture, courtesy, politeness) that build healthy relationships and take them ahead to life. In many parts of India, in many situations, and on formal occasions, it is common for people of India to express and exchange respect, greetings, and salutation for which we people usually use words and phrases like- Namaskar, Namaste, Pranam, Ram Ram, Jai Ram ji, Jai Sriram, Good morning, shubha sakal, Radhe Radhe, Jai Bajarangabali, Jai Gopal, Jai Jai, Supravat, Good night, Shuvaratri, Jai Bhole, Salaam walekam, Walekam salaam, Radhaswami, Namo Buddhaya, Jai Bhim, Hello, and so on. A soft attitude always creates strong relationships. A relationship should not depend only on spoken words. They should rely on understanding the unspoken feeling too. So w...

राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी: जल जीवन मिशन के लक्ष्य को पाने समन्वित प्रयास जरूरी

- राज कुमार सिन्हा*  जल संसाधन से जुड़ी स्थायी समिति ने वर्तमान लोकसभा सत्र में पेश रिपोर्ट में बताया है कि "नल से जल" मिशन में राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी साबित हुए हैं। जबकि देश के 11 राज्यों में शत-प्रतिशत ग्रामीणों को नल से जल आपूर्ति शुरू कर दी गई है। रिपोर्ट में समिति ने केंद्र सरकार को सिफारिश की है कि मिशन पुरा करने में राज्य सरकारों की समस्याओं पर गौर किया जाए। 

Aurangzeb’s last will recorded by his Maulvi: Allah shouldn't make anyone emperor

By Mohan Guruswamy  Aurangzeb’s grave is a simple slab open to the sky lying along the roadside at Khuldabad near Aurangabad. I once stopped by to marvel at the tomb of an Emperor of India whose empire was as large as Ashoka the Great's. It was only post 1857 when Victoria's domain exceeded this. The epitaph reads: "Az tila o nuqreh gar saazand gumbad aghniyaa! Bar mazaar e ghareebaan gumbad e gardun bas ast." (The rich may well construct domes of gold and silver on their graves. For the poor folks like me, the sky is enough to shelter my grave) The modest tomb of Aurangzeb is perhaps the least recognised legacies of the Mughal Emperor who ruled the land for fifty eventful years. He was not a builder having expended his long tenure in war and conquest. Towards the end of his reign and life, he realised the futility of it all. He wrote: "Allah should not make anyone an emperor. The most unfortunate person is he who becomes one." Aurangzeb’s last will was re...

PUCL files complaint with SC against Gujarat police, municipal authorities for 'unlawful' demolitions, custodial 'violence'

By A Representative   The People's Union for Civil Liberties (PUCL) has lodged a formal complaint with the Chief Justice of India, urging the Supreme Court to initiate suo-moto contempt proceedings against the police and municipal authorities in Ahmedabad, Gujarat. The complaint alleges that these officials have engaged in unlawful demolitions and custodial violence, in direct violation of a Supreme Court order issued in November 2024.

Incarcerated for 2,424 days, Sudhir Dhawale combines Ambedkarism with Marxism

By Harsh Thakor   One of those who faced incarceration both under Congress and BJP rule, Sudhir Dhawale was arrested on June 6, 2018, one of the first six among the 16 people held in what became known as the Elgar Parishad case. After spending 2,424 days in incarceration, he became the ninth to be released from jail—alongside Rona Wilson, who walked free with him on January 24. The Bombay High Court granted them bail, citing the prolonged imprisonment without trial as a key factor. I will always remember the moments we spent together in Mumbai between 1998 and 2006, during public meetings and protests across a wide range of issues. Sudhir was unwavering in his commitment to Maoism, upholding the torch of B.R. Ambedkar, and resisting Brahmanical fascism. He sought to bridge the philosophies of Marxism and Ambedkarism. With boundless energy, he waved the banner of liberation, becoming the backbone of the revolutionary democratic centre in Mumbai and Maharashtra. He dedicated himself ...

Censor Board's bullying delays 'Phule': A blow to India's democratic spirit

By Vidya Bhushan Rawat*  A film based on the life and legacy of Jyotiba Phule and Savitribai Phule was expected to release today. Instead, its release has been pushed to the last week of April. The reason? Protests by self-proclaimed guardians of caste pride—certain Brahmin groups—and forced edits demanded by a thoroughly discredited Censor Board.

How Mumbai University crumbles: Not just its buildings

By Rosamma Thomas*  In recent days, the news from the University of Mumbai has been far from inspiring – clumps of plaster have fallen off the ceiling at the CD Deshmukh Bhavan, and it was good fortune that no one was injured; creepy crawlies were found in the water dispenser that students use to collect drinking water, and timely warning videos circulated by vigilant students have kept people safe so far.

Beyond his riding skill, Karl Umrigar was admired for his radiance, sportsmanship, and affability

By Harsh Thakor*  Karl Umrigar's name remains etched in the annals of Indian horse racing, a testament to a talent tragically cut short. An accident on the racetrack at the tender age of nineteen robbed India of a rider on the cusp of greatness. Had he survived, there's little doubt he would have ascended to international stature, possibly becoming the greatest Indian jockey ever. Even 46 years after his death, his name shines brightly, reminiscent of an inextinguishable star. His cousin, Pesi Shroff, himself blossomed into one of the most celebrated jockeys in Indian horse racing.

State Human Rights Commission directs authorities to uphold environmental rights in Vadodara's Vishwamitri River Project

By A Representative  The Gujarat State Human Rights Commission (GSHRC) has ordered state and Vadodara municipal authorities to strictly comply with environmental and human rights safeguards during the Vishwamitri River Rejuvenation Project, stressing that the river’s degradation disproportionately affects marginalized communities and violates citizens’ rights to a healthy environment.  The Commission mandated an immediate halt to ecologically destructive practices, rehabilitation of affected communities, transparent adherence to National Green Tribunal (NGT) orders, and public consultations with experts and residents.   The order follows the Concerned Citizens of Vadodara coalition—environmentalists, ecologists, and urban planners—submitting a detailed letter to authorities, amplifying calls for accountability. The group warned that current plans to “re-section” and “desilt” the river contradict the NGT’s 2021 Vishwamitri River Action Plan, which prioritizes floodpla...

CPM’s evaluation of BJP reflects its political character and its reluctance to take on battle against neo-fascism

By Harsh Thakor*  A controversial debate has emerged in the revolutionary camp regarding the Communist Party of India (Marxist)'s categorization of the Bharatiya Janata Party. Many Communists criticize the CPM’s reluctance to label the BJP as a fascist party and India as a fascist state. Various factors must be considered to arrive at an accurate assessment. Understanding the original meaning and historical development of fascism is essential, as well as analyzing how it manifests in the present global and national context.