No official documents exist showing eco-clearance for Garudeshwar Weir

Villagers protest against Garudeshwar Dam
By Rohit Prajapati, Lakhan Musafir*
In our case against Garudeshwar Weir (being set up about 12 km downstream of the Sardar Sarovar Dam in Narmada river) in the National Green Tribunal (NGT), the Ministry of Environment and Forests (MoEF), has said, “… no project proposal regarding Garudeshwar Weir at Garudeshwar village, District Narmada of Gujarat, has been received in this Ministry.” The Sardar Sarovar Narmada Nigam Ltd (SSNNL) has said, its affidavit is only for “the limited purpose”, it is “not dealing with the application parawise”, nor it is “giving elaborate details which would show that construction of Garudeshwar Weir is strictly in conformity with law.” It is now clear: the SSNNL has no documents to show and prove that the construction of Garudeshwar Weir is going on as per the law.
In their replies the MoEF, the Narmada Control Authority (NCA) and the SSNNL do not deny our contention that:There has never been an environment and social impact assessment of the Garudeshwar weir, nor is there any environment and social management plan,
There has never been any public consultation on the issue of Garudeshwar Dam, and
The Garudeshwar Dam requires statutory clearances from the Environment Sub Group, Rehabilitation Sub Group of the NCA and also the NCA itself, but such clearances have not been taken.
In view of this, as mentioned in our petition, the work on Garudeshwar Dam, now going on, is illegal and should immediately stop till all necessary statutory clearances are taken, and till informed consultation process is completed.

MoEF wants to be excused

The MoEF, in its reply filed before the NGT on May 29, 2014, in response to our Application No 10/2014 (WZ) stated, “No project proposal regarding Garudeshwar Weir at Garudeshwar Village, District Narmada of Gujarat has been received in this Ministry.” It has become clear that at no point of time the construction of Garudeshwar Weir had come before it for environmental clearance.
The MoEF implicitly agrees with our contention that the Garudeshwar Dam is a project for which no impact assessment was available before it at any stage. This implies that the affected villages, next to the weir, were neither surveyed, nor environmental and social impact was made known, nor were mitigation and management plans prepared, nor were there any consultations. The impact assessment of Garudeshwar Dam was not part of the studies submitted by Gujarat to the MoEF before the 1987 environmental clearance of the Sardar Sarovar Project (SSP). Thus, environmental clearance for SSP cannot be construed as clearance for Garudeshwar Weir.
The MoEF is not denying the contents of letter dated March 24, 2013 written by Shekhar Singh, an independent member of environment sub-group of the NCA (the statutory body responsible for clearance before taking up construction for the SSP at every stage), and the letters dated October 26 and 28, 2013 of the Paryavaran Suraksha Samiti and villagers. The MoEF only states in its affidavit, “…copies of the letter dated 24.3.2013 by Mr. Shekhar Singh, Member, ESG, Narmada Control Authority and letter dated 26.10.2013 by Applicants could not be traced in the Ministry. Therefore, no responses were made on the subject.”
The Supreme Court order dated October 18, 2000 in the case of Narmada Bachao Andolan v/s Union of India and others states that environment clearance for the Narmada project, approval of the environment sub-group (ESG) and rehabilitation & resettlement sub-group (RSG) of the NCA are necessary at each stage of project construction. Without such explicit approval, the construction of any component of the project cannot be taken up. Since construction of Garudeshwar Weir has not been approved by the ESG and RSG of the NCA at any stage, such construction is illegal and should be stopped.
The MoEF in its affidavit at the end states, “As per contents of the petition, MoEF is not having any role to play in the present petition. Therefore, MoEF may not be made a party in the present Petition.”
But MoEF is an environmental regulator of India, which is responsible for the protection of environment and forest in general, and the secretary, MoEF, is also a chairman of the ESG of NCA. The MoEF cannot shirk its responsibility and it is shocking to see MoEF shirking its responsibility.

NCA’s untenable reply

The executive engineer of the NCA filed a reply on behalf of the chairman of the environment and rehabilitation sub-groups of the NCA, the chairman of the NCA, secretary of the Ministry of Social Justice and Empowerment, and also secretary of the Ministry of Water Resources! This is clearly a legally untenable act. The executive engineer of the NCA does not have legal authority and mandate to file joint reply on behalf of these bodies, which have very specific and different roles. Clubbing them in one reply is not only violation of the cause of environment, rehabilitation, water resources development and independent and statutory groups and authorities; it would do disservice to the interests these authorities and ministries are supposed to protect. The affidavit is also in violation of the basic principle of judicial process and hence should be rejected.
The reply is nowhere disputing our contention that social or environmental impact assessment of the construction of Garudeshwar Weir has not been taken up at any stage. Nor is the reply disputing our contention that no participatory decision making process has been followed before starting the construction of the Garudeshwar Weir, involving the affected people and other interest groups.
The reply is also not disputing our contention that at no stage the permissions of the environment sub-group, rehabilitation sub-group, and participating states have been taken for the construction of the Garudeshwar Weir.
In fact the reply is so callous that it does not even bother to state what the impact of the Garudeshwar Dam would be. The reply does not go into merits of the issues about the impact of the Garudeshwar Dam and what has been done about that. It only contends that the application should be dismissed on procedural grounds, and just to contend this, it has taken more than four months, which is clearly an abuse of the time given to it.
If indeed any social and environmental impact assessment of the Garudeshwar Dam has been done, or the authorities have taken and/or expressed and specific permission of the environment and rehabilitation sub-groups of the NCA and the NCA, then this should have been produced. Taking up construction of the Garudeshwar Weir is in violation of the due process, including that of the Supreme Court order.

The SSNNL reply

The reply filed by the SSNNL after taking more than four months is vague; it has tried its best to avoid addressing the basic crucial issue of the furnishing the mandated environmental impact assessment and environment clearance of Garudeshwar Weir.
The SSNNL representative in the reply states “… I am filing this affidavit only for the limited purpose as aforesaid, I am not dealing with the application parawise at this stage nor am I giving elaborate details which would show that construction of Garudeshwar Weir is strictly in conformity with law.” By stating “… nor am I giving elaborate details which would show that construction of Garudeshwar Weir is strictly in conformity with law”, the SSNNL reply makes it crystal clear that it does not have documents to show and prove that the construction of Garudeshwar Weir is going on as per law. It also does not have documents to show that it obtained the necessary environment clearance from the concerned authority.
The SSNNL in its reply further states, “At the outset, I beg to raise the following preliminary objections as regards the maintainability of the present application under the National Green Tribunal Act, 2010 which is purported to have been filed under Section 18(1) read with Section 14 and 15 of the National Green Tribunal Act, 2010. I respectfully pray that the below mentioned preliminary objections be decided first.” This is a ploy adopted by the SSNNL to delay the case and continue with the illegal construction work to defeat the process of justice.

Our Response

We had filed our affidavits in rejoinder, in response to all the affidavits filed by the authorities, and raised above-mentioned issues in our affidavits, and demanded stoppage of irreversible nature of work carried out by the SSNNL for Garudeshwar Weir. Considering that none of the concerned authorities have been able to produce either impact assessment or environment clearance obtained from the MoEF and from the environment and R&R sub-groups of the NCA, the NGT should immediately order stoppage of work.

*Representing Paryavaran Suraksha Samiti, Vadodara, which has filed a petition in the National Green Tribunal to immediately stop work the Garudeshwar Weir, 12 km off Sardar Sarovar dam

Comments

TRENDING

How the slogan Jai Bhim gained momentum as movement of popularity and revolution

By Dr Kapilendra Das*  India is an incomprehensible plural country loaded with diversities of religions, castes, cultures, languages, dialects, tribes, societies, costumes, etc. The Indians have good manners/etiquette (decent social conduct, gesture, courtesy, politeness) that build healthy relationships and take them ahead to life. In many parts of India, in many situations, and on formal occasions, it is common for people of India to express and exchange respect, greetings, and salutation for which we people usually use words and phrases like- Namaskar, Namaste, Pranam, Ram Ram, Jai Ram ji, Jai Sriram, Good morning, shubha sakal, Radhe Radhe, Jai Bajarangabali, Jai Gopal, Jai Jai, Supravat, Good night, Shuvaratri, Jai Bhole, Salaam walekam, Walekam salaam, Radhaswami, Namo Buddhaya, Jai Bhim, Hello, and so on. A soft attitude always creates strong relationships. A relationship should not depend only on spoken words. They should rely on understanding the unspoken feeling too. So w...

राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी: जल जीवन मिशन के लक्ष्य को पाने समन्वित प्रयास जरूरी

- राज कुमार सिन्हा*  जल संसाधन से जुड़ी स्थायी समिति ने वर्तमान लोकसभा सत्र में पेश रिपोर्ट में बताया है कि "नल से जल" मिशन में राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी साबित हुए हैं। जबकि देश के 11 राज्यों में शत-प्रतिशत ग्रामीणों को नल से जल आपूर्ति शुरू कर दी गई है। रिपोर्ट में समिति ने केंद्र सरकार को सिफारिश की है कि मिशन पुरा करने में राज्य सरकारों की समस्याओं पर गौर किया जाए। 

Censor Board's bullying delays 'Phule': A blow to India's democratic spirit

By Vidya Bhushan Rawat*  A film based on the life and legacy of Jyotiba Phule and Savitribai Phule was expected to release today. Instead, its release has been pushed to the last week of April. The reason? Protests by self-proclaimed guardians of caste pride—certain Brahmin groups—and forced edits demanded by a thoroughly discredited Censor Board.

PUCL files complaint with SC against Gujarat police, municipal authorities for 'unlawful' demolitions, custodial 'violence'

By A Representative   The People's Union for Civil Liberties (PUCL) has lodged a formal complaint with the Chief Justice of India, urging the Supreme Court to initiate suo-moto contempt proceedings against the police and municipal authorities in Ahmedabad, Gujarat. The complaint alleges that these officials have engaged in unlawful demolitions and custodial violence, in direct violation of a Supreme Court order issued in November 2024.

Aurangzeb’s last will recorded by his Maulvi: Allah shouldn't make anyone emperor

By Mohan Guruswamy  Aurangzeb’s grave is a simple slab open to the sky lying along the roadside at Khuldabad near Aurangabad. I once stopped by to marvel at the tomb of an Emperor of India whose empire was as large as Ashoka the Great's. It was only post 1857 when Victoria's domain exceeded this. The epitaph reads: "Az tila o nuqreh gar saazand gumbad aghniyaa! Bar mazaar e ghareebaan gumbad e gardun bas ast." (The rich may well construct domes of gold and silver on their graves. For the poor folks like me, the sky is enough to shelter my grave) The modest tomb of Aurangzeb is perhaps the least recognised legacies of the Mughal Emperor who ruled the land for fifty eventful years. He was not a builder having expended his long tenure in war and conquest. Towards the end of his reign and life, he realised the futility of it all. He wrote: "Allah should not make anyone an emperor. The most unfortunate person is he who becomes one." Aurangzeb’s last will was re...

Incarcerated for 2,424 days, Sudhir Dhawale combines Ambedkarism with Marxism

By Harsh Thakor   One of those who faced incarceration both under Congress and BJP rule, Sudhir Dhawale was arrested on June 6, 2018, one of the first six among the 16 people held in what became known as the Elgar Parishad case. After spending 2,424 days in incarceration, he became the ninth to be released from jail—alongside Rona Wilson, who walked free with him on January 24. The Bombay High Court granted them bail, citing the prolonged imprisonment without trial as a key factor. I will always remember the moments we spent together in Mumbai between 1998 and 2006, during public meetings and protests across a wide range of issues. Sudhir was unwavering in his commitment to Maoism, upholding the torch of B.R. Ambedkar, and resisting Brahmanical fascism. He sought to bridge the philosophies of Marxism and Ambedkarism. With boundless energy, he waved the banner of liberation, becoming the backbone of the revolutionary democratic centre in Mumbai and Maharashtra. He dedicated himself ...

Why crucifixion is a comprehensive message of political journey for the liberation of the oppressed

By Vijayan MJ  Passion week is that time of the year when Christians all over the world remind themselves about the sufferings, anguish, pain and the bloody crucifixion that Jesus Christ took on himself, as part of his mission of emancipating the people and establishing the kingdom of god. The crucifixion was not just a great symbolism of the personal sacrifice of one person, but it was a comprehensive messaging of a political journey for the liberation of the oppressed; one filled with struggle, militancy, celebration of life, rejection of temptations, betrayals, grief, the long-walk with the cross, crucifixion and ultimately resurrection as a symbol of victory over the oppressors and evil. 

CPM’s evaluation of BJP reflects its political character and its reluctance to take on battle against neo-fascism

By Harsh Thakor*  A controversial debate has emerged in the revolutionary camp regarding the Communist Party of India (Marxist)'s categorization of the Bharatiya Janata Party. Many Communists criticize the CPM’s reluctance to label the BJP as a fascist party and India as a fascist state. Various factors must be considered to arrive at an accurate assessment. Understanding the original meaning and historical development of fascism is essential, as well as analyzing how it manifests in the present global and national context.

Akhilesh Yadav’s boycott of Dainik Jagran: A step towards accountability or political rhetoric?

By Vidya Bhushan Rawat  Akhilesh Yadav has called for a total boycott of Dainik Jagran, a newspaper owned by the Gupta family. He also declared that the Samajwadi Party will no longer participate in any panel discussions organized by a media channel allegedly controlled by the family or relatives of the omnipresent Rajiv Shukla. Akhilesh Yadav and the Samajwadi Party are well aware that Dainik Jagran has long been antagonistic to Dalit-Bahujan interests. The newspaper represents a Bania-Brahmin corporate and ideological enterprise.

How Mumbai University crumbles: Not just its buildings

By Rosamma Thomas*  In recent days, the news from the University of Mumbai has been far from inspiring – clumps of plaster have fallen off the ceiling at the CD Deshmukh Bhavan, and it was good fortune that no one was injured; creepy crawlies were found in the water dispenser that students use to collect drinking water, and timely warning videos circulated by vigilant students have kept people safe so far.