People of Odisha have not yet given up struggle against Posco, which has "acquired" 2,700 acres for steel project

By Kanchi Kohli*
The battlelines have been drawn like never before. While the Odisha state government and Posco India Ltd have made categorical statements that they have acquired 2,700 acres for an eight million tonnes steel project, the agitations in Gobindpur and Dhinkia continue. Each day there are incidents of a tussle when efforts are made to forcibly cut betel vines and dig trenches to construct a boundary wall for the Posco project. There are emphatic statements that land acquisition has been completed, all permissions are in place and construction work will begin soon.
From the other side, there are determined statements that indicate that people of the area have not given up despite an eight-year struggle. They are ready to return to their homes and their betel vines that have been destroyed in the tussle for power. Far away from the site of the contest, legal battles and the opinions of experts continue to ascertain the future of the people of Jagatsinghpur where an investment of `52,000 crore is directed at the construction of a captive steel plant, power plant and port. Many livelihoods dependant on betel vine cultivation, agriculture and fishing in the villages of Dhinkia, Gobindapur, Nuagaon, Polanga, Bhuyanpai, Bayanal, Kandah, Noliasahi and Jatadhar will be affected by the project.
When Posco signed its MoU with the Odisha government way back in 2005, their intention was to set up a 12 MTPA steel plant along with several other components of the project. The first public hearing for the project in April 2007 was for the construction of a 4 MTPA steel plant, a 400 MW power plant along with a captive port. Even as permissions for the above were granted in July and May 2007 respectively, Posco continued to acquire land keeping in mind its final steel plant of 12 MTPA. Posco’s website says they will complete the project in three phases, constructing the steel plant to accommodate 4 MTPA capacity each time, with the first phase to be completed by 2016-17.
With various legal issues and battles on the ground, alongside assessments commissioned by the Union Ministry of Environment and Forests (MoEF), Posco first received its environment clearance in 2007 which was reviewed through the recommendations of the MoEF constituted Meena Gupta Committee’s reports in 2010. A final environment clearance (issued under the Environment Impact Assessment notification, 2006) was granted on January 31, 2011. For all practical purposes this was to be considered the final clearance as project activity had not begun on the proposed site. In May and June 2012, the environment clearances granted to Posco in 2007 also expired given that they were to be valid only for a period of five years.
Meanwhile both the 2011 and 2007 approvals were challenged before the National Green Tribunal (NGT). The tribunal on 30 March 2012 issued a strong judgment upholding that there was indeed a lacuna in the manner in which the approval for Posco had been granted. The tribunal said that it was necessary to ensure optimum use of land (both forest and non-forest) being acquired for Posco keeping in mind a 4 MTPA plant. The company had carried out an Environment Impact Assessment (EIA) as well as the public hearing process on the basis of this capacity. Based on this and several other contentions a fresh review of the environment clearance was to take place.
In mid 2012, two parallel processes began in the MoEF. The first was the process of revalidation of the 2007 clearances and the second the setting up of an expert committee under K.Roy Paul, Former Secretary to the Government of India. The process of revalidation and the review by the Roy Paul committee took place simultaneously till all the documents were placed in a meeting of the MoEF Expert Appraisal Committee (EAC) for industrial projects in March 2013. In this meeting Posco contented that while they are currently pursuing the plan for a 4 MTPA plant, their final intention is to set up a 12 MTPA plant which has not changed. At this stage the EAC sought a revised layout design for not just a 4 MTPA plant but also an 8 MTPA one. 
Many of the contentions made in the Roy Paul Committee report which was submitted to the MoEF in October 2012 did not seem to have been discussed by the EAC, if one is to go by the official minutes of the meeting. In fact the Roy Paul committee had recommended that a range of studies should be carried out by the project proponent related to shoreline changes, source sustainability study of water requirement, marine environmental conservation plan, the impact on the local fishing community etc, which don’t find mention as well.
One of the foremost observations of the Roy Paul committee was that Posco should state unambiguously whether the reduced project area based on land optimisation for 4 MTPA will be able to accommodate all its future expansion plans. The report observes that based on information provided, the project area had been reduced to 2,700 acres by leaving out most of the private land in Govindpur and Dhinkia villages and the portion of forest land where betel vines were being grown by people of these villages. This implies that the project would be constructed around these villages implying these lands are not to be acquired only in the current proposal.
In the subsequent meeting of the EAC of 16-17th May this year, the expert committee recommended the revalidation of the approval for an 8 MTPA plant. What is ironic is that the original application as well as the EIA report of 2007 is all based on the impact assessment of a plant of 4 MTPA capacity. Although the final approval letter from the MoEF is yet to be issued, it is questionable how an approval for 8 MTPA has been recommended by the EAC.
Posco’s legal tussles are also back in the NGT in another form. An application has been filed highlighting that Posco has been carrying out felling of trees on 1253.225 ha of forest land without the final forest clearance order being issued by the Odisha state government. This application builds on the reiteration and interpretation of both the Forest Conservation Act (FCA) 1980, by the NGT Act which states that the permission for diverting forest land for non-forest purposes under Section 2 of the FCA by the MoEF needs to be followed by an order of the state government as well. No construction work on the project can begin till the order of the state government has been issued. In Posco’s case this has not happened.
As per a Right to Information (RTI) response received on March 13 this year to an application filed by Chandranath Dani, the Odisha state government has confirmed that no such order has been issued. Based on this and additional contentions the NGT on May 28 stayed the felling of trees by the company. On July 11 this order was allowed to continue till the next hearing of the case on  August 12.
There are other legal procedures that are likely to crop up for Posco. In the 16th May meeting of the EAC (Industry) a recommendation has been made that Posco should obtain an additional CRZ clearance for discharge of wastewater into the sea through a pipeline. This process is yet to begin.
For the people of India the eight-year-old tryst with Posco has many lessons. There are international and national reports highlighting a list of human rights and regulatory violations that the history of the project is marred with. In Jagatsinghpur, each day is a new day for villagers who don’t know what form of aggression will come their way and how they will be able to withstand it. The fact is that the people of the area have not given up. What is clear for now is that Posco is certainly not a closed chapter.
---
* Kanchi Kohli is a well-known researcher and publicist on environment governance and biodiversity conservation related issues

Comments

TRENDING

Beyond his riding skill, Karl Umrigar was admired for his radiance, sportsmanship, and affability

By Harsh Thakor*  Karl Umrigar's name remains etched in the annals of Indian horse racing, a testament to a talent tragically cut short. An accident on the racetrack at the tender age of nineteen robbed India of a rider on the cusp of greatness. Had he survived, there's little doubt he would have ascended to international stature, possibly becoming the greatest Indian jockey ever. Even 46 years after his death, his name shines brightly, reminiscent of an inextinguishable star. His cousin, Pesi Shroff, himself blossomed into one of the most celebrated jockeys in Indian horse racing.

राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी: जल जीवन मिशन के लक्ष्य को पाने समन्वित प्रयास जरूरी

- राज कुमार सिन्हा*  जल संसाधन से जुड़ी स्थायी समिति ने वर्तमान लोकसभा सत्र में पेश रिपोर्ट में बताया है कि "नल से जल" मिशन में राजस्थान, मध्यप्रदेश, पश्चिम बंगाल, झारखंड और केरल फिसड्डी साबित हुए हैं। जबकि देश के 11 राज्यों में शत-प्रतिशत ग्रामीणों को नल से जल आपूर्ति शुरू कर दी गई है। रिपोर्ट में समिति ने केंद्र सरकार को सिफारिश की है कि मिशन पुरा करने में राज्य सरकारों की समस्याओं पर गौर किया जाए। 

Aurangzeb’s last will recorded by his Maulvi: Allah shouldn't make anyone emperor

By Mohan Guruswamy  Aurangzeb’s grave is a simple slab open to the sky lying along the roadside at Khuldabad near Aurangabad. I once stopped by to marvel at the tomb of an Emperor of India whose empire was as large as Ashoka the Great's. It was only post 1857 when Victoria's domain exceeded this. The epitaph reads: "Az tila o nuqreh gar saazand gumbad aghniyaa! Bar mazaar e ghareebaan gumbad e gardun bas ast." (The rich may well construct domes of gold and silver on their graves. For the poor folks like me, the sky is enough to shelter my grave) The modest tomb of Aurangzeb is perhaps the least recognised legacies of the Mughal Emperor who ruled the land for fifty eventful years. He was not a builder having expended his long tenure in war and conquest. Towards the end of his reign and life, he realised the futility of it all. He wrote: "Allah should not make anyone an emperor. The most unfortunate person is he who becomes one." Aurangzeb’s last will was re...

How the slogan Jai Bhim gained momentum as movement of popularity and revolution

By Dr Kapilendra Das*  India is an incomprehensible plural country loaded with diversities of religions, castes, cultures, languages, dialects, tribes, societies, costumes, etc. The Indians have good manners/etiquette (decent social conduct, gesture, courtesy, politeness) that build healthy relationships and take them ahead to life. In many parts of India, in many situations, and on formal occasions, it is common for people of India to express and exchange respect, greetings, and salutation for which we people usually use words and phrases like- Namaskar, Namaste, Pranam, Ram Ram, Jai Ram ji, Jai Sriram, Good morning, shubha sakal, Radhe Radhe, Jai Bajarangabali, Jai Gopal, Jai Jai, Supravat, Good night, Shuvaratri, Jai Bhole, Salaam walekam, Walekam salaam, Radhaswami, Namo Buddhaya, Jai Bhim, Hello, and so on. A soft attitude always creates strong relationships. A relationship should not depend only on spoken words. They should rely on understanding the unspoken feeling too. So w...

PUCL files complaint with SC against Gujarat police, municipal authorities for 'unlawful' demolitions, custodial 'violence'

By A Representative   The People's Union for Civil Liberties (PUCL) has lodged a formal complaint with the Chief Justice of India, urging the Supreme Court to initiate suo-moto contempt proceedings against the police and municipal authorities in Ahmedabad, Gujarat. The complaint alleges that these officials have engaged in unlawful demolitions and custodial violence, in direct violation of a Supreme Court order issued in November 2024.

Incarcerated for 2,424 days, Sudhir Dhawale combines Ambedkarism with Marxism

By Harsh Thakor   One of those who faced incarceration both under Congress and BJP rule, Sudhir Dhawale was arrested on June 6, 2018, one of the first six among the 16 people held in what became known as the Elgar Parishad case. After spending 2,424 days in incarceration, he became the ninth to be released from jail—alongside Rona Wilson, who walked free with him on January 24. The Bombay High Court granted them bail, citing the prolonged imprisonment without trial as a key factor. I will always remember the moments we spent together in Mumbai between 1998 and 2006, during public meetings and protests across a wide range of issues. Sudhir was unwavering in his commitment to Maoism, upholding the torch of B.R. Ambedkar, and resisting Brahmanical fascism. He sought to bridge the philosophies of Marxism and Ambedkarism. With boundless energy, he waved the banner of liberation, becoming the backbone of the revolutionary democratic centre in Mumbai and Maharashtra. He dedicated himself ...

State Human Rights Commission directs authorities to uphold environmental rights in Vadodara's Vishwamitri River Project

By A Representative  The Gujarat State Human Rights Commission (GSHRC) has ordered state and Vadodara municipal authorities to strictly comply with environmental and human rights safeguards during the Vishwamitri River Rejuvenation Project, stressing that the river’s degradation disproportionately affects marginalized communities and violates citizens’ rights to a healthy environment.  The Commission mandated an immediate halt to ecologically destructive practices, rehabilitation of affected communities, transparent adherence to National Green Tribunal (NGT) orders, and public consultations with experts and residents.   The order follows the Concerned Citizens of Vadodara coalition—environmentalists, ecologists, and urban planners—submitting a detailed letter to authorities, amplifying calls for accountability. The group warned that current plans to “re-section” and “desilt” the river contradict the NGT’s 2021 Vishwamitri River Action Plan, which prioritizes floodpla...

CPM’s evaluation of BJP reflects its political character and its reluctance to take on battle against neo-fascism

By Harsh Thakor*  A controversial debate has emerged in the revolutionary camp regarding the Communist Party of India (Marxist)'s categorization of the Bharatiya Janata Party. Many Communists criticize the CPM’s reluctance to label the BJP as a fascist party and India as a fascist state. Various factors must be considered to arrive at an accurate assessment. Understanding the original meaning and historical development of fascism is essential, as well as analyzing how it manifests in the present global and national context.

Implications of deaths of Maoist leaders G. Renuka and Ankeshwarapu Sarayya in Chhattisgarh

By Harsh Thakor*  In the wake of recent security operations in southern Chhattisgarh, two senior Maoist leaders, G. Renuka and Ankeshwarapu Sarayya, were killed. These operations, which took place amidst a historically significant Maoist presence, resulted in the deaths of 31 individuals on March 20th and 16 more three days prior.

Haven't done a good deed, inner soul is cursing me as sinner: Aurangzeb's last 'will'

Counterview Desk The Tomb of Aurangzeb, the last of the strong Mughal emperors, located in Khuldabad, Aurangabad district, Maharashtra, has this epitaph inscribed on it: "Az tila o nuqreh gar saazand gumbad aghniyaa! Bar mazaar e maa ghareebaan gumbad e gardun bas ast" (the rich may well construct domes of gold and silver on their graves. For the poor folks like me, the sky is enough to shelter my grave).